March 2025 marked one year since the former Payneham Memorial Swimming Centre was demolished to make way for a modern state-of-the-art aquatic leisure centre.
Now at the halfway mark of the construction phase, much has been achieved and the three new swimming pools are taking shape — and water!
In November 2024, construction of the two indoor pool shells— the learn to swim and the 25 metre pools — were completed, closely followed in December by the outdoor 50 metre, 10 lane pool shell.
Following completion of the shells and associated works, the pools have successfully undergone hydrostatic testing.
“Hydrostatic testing is a crucial quality control measure to identify any potential leaks or structural weaknesses prior to completing construction,” says Michael Moshos, the Council’s Project Manager.
“We filled the pools with water to simulate usual operating conditions and observed over a nominated period to determine if there were any possible issues.
“We are pleased to report that the testing is complete, the pools have been drained and construction continued as planned.”
While the construction of the pools is underway, the building works around the pools have also been taking shape.
“Over December 2024 and January 2025, we saw the erection of the structural steel components and installation of roofing for the indoor pool hall,” says Michael.
“This is a significant milestone which made way for the internal fit out of the pool hall to commence in March 2025, closely followed by installation of the feature timber ceiling to commence in April.”
The next key milestones include the construction of the concrete slab for the pavilion building — the main entrance to the Centre that houses function and commercial areas — and installation of pool tiling and finishes for the 25 and 50 metre pools.
“Over the coming months, passers-by will start to see construction of the pavilion building — the main entrance to the Centre that houses function and commercial areas.”
Practical completion of the Payneham Memorial Swimming Centre is scheduled and on-track for early 2026.